Womy project · Industrial transport & lifting
ثلاثون خزاناً لصالح Cerveceria Cubana
Specialist transport and lifting for a new brewery in Mariel, with tanks weighing more than 30 tonnes each.
Mariel, Cuba


Swipe to view the photos
Womy transported and unloaded thirty tanks from the port to the brewery yard. The work used specialist transport combinations and a Liebherr LTM 1250-5.1 crane.
The published project plan also covers preparing the tanks with supports, moving them to their final positions and lifting them vertically onto foundations.
Equipment used
- Liebherr LTM 1250-5.1
- Scheuerle InterCombi & Euro Axle trailers
- Nooteboom semi-trailer
- Volvo 8×4 trucks