A coordinated lift and specialist road transport for turbine components weighing up to 140 tonnes.
Cienfuegos, Cuba


Swipe to view the photos
The ship’s cranes alone could not handle the heaviest component. Womy combined mobile cranes with the ship crane and a Multilug arrangement to distribute the load.
After unloading, the turbine parts travelled approximately 50 kilometres on specialist transport equipment. The project brought lifting and road logistics together in one operation.
Equipment used
- Liebherr LTM 1220-5.1
- Liebherr LTM 1160-5.2
- Scheuerle InterCombi · 9 axles
- Volvo FH16 8×4